FORMULAS RELATED TO POWER PLANT PERFORMANCE INDICES: (Actual operating hours + Restricted S/D hours)*100 AVAILABILITY FACTOR (%) = 24 LOADING FACTOR (%) =
(Actual generation in a day in MU )X 100 (Actual operating hours X 0.125)
( Actual generation in a day in MU) X 100 PLANT LOAD FACTOR (%) = (24 X 0.125) GENERATOR ON LINE (%) =
( Actual operating hours) *100 24
(Availability factor - PLF) * 100 PARTIAL LOADING (%) = Availability factor AUXILIARY POWER CONSUMPTION (%) = SPECIFIC OIL CONSUMPTION (ml/kWh) =
Actual power consumption in MWh* 100 Actual generation in MWh ( Actual oil consumption in KL)*100 Actual generation in MU
Actual lignite consumption in MT x 100 SPECIFIC LIGNITE CONSUMPTION (kg/kWh) = Actual generation in MWh (Actual SG makeup consumption in MT X act Running hours) SG MAKEUP CONSUMPTION (MT) = 24 SG MAKEUP CONSUMPTION (%MCR) =
SG makeup consumption in MT x 100 (Actual running hours X 390)
Net export inc. colony & mines in MU COMMERCIAL AVAILABILITY IN MU = .9 Dump power in MWh 9000
-
Deemed non generation in MWh 90
COMMERCIAL AVAILABILITY (%) =
(Commercial availability in MU) * 100 6.000 X No. Of days
GENERATION LOSS GRID/LIGNITE (MU) =
PLF LOSS GRID/LIGNITE (%) =
+ Deemed generation in MU
Deemed generation in MWh 900
(Generation loss grid/lignite in MU) * 100 (24 X 0.125)
DEEMED GENERATION IN MU = Generation loss grid/lignite in MU + Actual generation in MU